The Owen Springs plant, located near Alice Springs, will be constructed by MAN Diesel & Turbo for Power and Water Corporation (PWC), a public utility owned by the Northern Territory Government. Commissioning of the first engine is expected in July 2010, and the complete power station is expected to be handed over to PWC in October 2010.

The project is based on three 10.9 megawatt (MW) generator sets, each powered by a twelve-cylinder, vee-configuration 12V51/60DF engine. The generator sets will supply base load power to the local grid in their gaseous-fuel mode – burning natural gas ignited by a distillate fuel ‘micro-pilot’.

At the time of signing the contract in 2008, PWC’s General Manager of Generation John Linton said that the contract specifications were technically complex, as PWC was seeking world’s best practice in fuel efficiency and the lowest emissions of carbon dioxide per unit of electricity generated.

PWC has 360 MW of existing power generation capacity and services more than 80,000 customers.

Article continues below…

Owen Springs’ development

Stage One of the Owens Springs project, which covers the construction of the power house, control room, switchroom, administration centre, tank farm, pump house and maintenance workshop buildings, will be completed on schedule in May 2010.

Power house construction commenced in October 2009, utilising a concrete-panel design to form the exterior and interior walls. These panels were formed onsite and are characterised by their high quality sound attenuation properties, low construction costs and fast installation.

Once installed, a supporting steel framework was erected and fastened and the exterior was painted to complete the building.

The next phase, comprising the installation of mechanical and electrical systems, is now underway. Piping is already largely complete, while the installation of lube-oil and fuel-oil modules has commenced.

MAN Diesel Australia has also formed partnerships with local Australian suppliers and stakeholders, as much of the equipment for the Owen Springs project must comply with Australian standards.

A project milestone

The arrival of the first of Owen Springs’ three 10.9 MW generator sets marks a significant milestone for the project. The engine was originally loaded aboard a ship in Saint Nazaire, France in February 2010. It arrived in Darwin in early April from where its 230 tonne bulk was transported to the site using multiple prime movers and a low loading trailer. The land journey took some six days via a carefully planned 1,500 km route.